Committee refers Bagley Road resurfacing termini change to second reading to use excess federal funds

Cuyahoga County Public Works Procurement & Contracting Committee · May 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The procurement and contracting committee referred Resolution 20250188 to second reading after members approved substitute language extending the Bagley Road resurfacing limit in Berea by about 0.2 miles so the city can use excess federal funding; county staff said the extension requires no additional county money.

Cuyahoga County’s Public Works procurement and contracting committee on May 21 referred a resolution that would extend the termini of a planned Bagley Road resurfacing project in the city of Berea so the county and city can maximize available federal funds.

Nicole English of the county’s Public Works department told the committee the city asked to extend the project roughly 0.2 miles — increasing the scope from about 0.8 miles to roughly 1.0 mile — to take advantage of excess federal funding that became available during project development. "They actually had excess federal funding," English said, and the city requested the extended limits. English added the change would not require additional county money and that staff were finalizing the written language so the limits and funding line up before selling the project.

The committee discussed wording in the draft preamble and substitute language that includes the new termini. Mister Miller moved to accept the substitute language updating the project endpoints; the motion was seconded and approved on a voice vote. Miller then moved that Resolution 20250188 be referred favorably for a second reading; the committee seconded and approved that referral on a voice vote. The committee’s record shows voice votes but does not include a numeric roll-call tally on the record.

Why it matters: changing the project termini allows the county and the city of Berea to stretch the resurfacing work slightly to the benefit of the local roadway network while using available federal funds. Committee members asked staff to ensure the written resolution reflects the new termini before the next reading.