Hector International sets Feb. 9 target to begin operations from new terminal addition; full renovation through 2026
Summary
Project manager reported the terminal addition’s ticketing and checkpoint work will phase into operation in February, with a February 9 target to begin using new gates and a March 1 target for the next phase; renovation of the existing concourse will continue through 2026.
The Hector International Municipal Airport Authority heard a progress report on the terminal addition and renovation on Dec. 16, as staff outlined a phased schedule to open new gates and move airlines into the expansion.
Maiden Hunt project representative Brandon told the board the team is finishing Level‑1 ticketing and Level‑2 finishes, coordinating with concession operator Skydine and working closely with TSA on the checkpoint migration. He said punch‑list work will begin in mid‑January and that the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat