City staff describe broken water meter, sewer-plant problems and repair estimate
Summary
Public works staff reported a broken water meter likely damaged by a contractor, invoicing to the responsible party, and sewer-plant troubles: pumps cannibalized for redundancy, a new flight-pump quote near $24,000, and plant cleanings planned to restore normal operations.
Get email alerts on the Utilities Infrastructure topic
No spam. Unsubscribe anytime.
Mona public-works staff told the City Council on Feb. 10 that a contractor bore through the side of a water meter can and that the city plans to invoice the responsible party for parts and overtime.
On sewer operations, staff described recent problems that reduced throughput and required interim repairs. One staff speaker reported: "We did 186,000 yesterday," describing recent treatment volumes, and later noted that the plant is treating more than it is receiving into the system at times. Staff said they cannibalized two older pumps to ensure redundancy while repairs proceed and reported a vendor quote for a new flight pump at roughly $24,000.
Staff said the plant equipment is aging — "Those are 14 years old," one speaker said — and outlined a plan for additional cleaning and repairs. They observed that some prior cleanings and maintenance routines (recommended every six months) were delayed after an earlier operational event, and staff expect to run an intensive schedule for the next one to two weeks to reduce the backlog.
Council and staff discussed whether the contractor responsible for damage should bear the full financial responsibility; staff said they had sent invoices for plumbing supplies and overtime and were tracking costs. The council discussed options for calling an external cleanup company if needed and asked staff to continue documenting repairs, costs and contract terms.
No formal council action was taken at the meeting specifically to authorize capital spending for a new pump; staff said they will obtain quotes and return with additional details if a purchase is required.
Next steps: staff will continue repairs, finalize vendor quotes for pump replacement, and follow up with the council if a purchase or budget amendment is needed.