Commissioners approve request to extend grant timeline for St. Joseph–Spencerville treatment project
Summary
Commonwealth Engineers told commissioners construction delays at St. Joseph–Spencerville were caused by poor soils and severe winter weather; commissioners authorized staff to sign and send an extension request to the grantor and approved the letter 3–0.
Get email alerts on the Infrastructure Project topic
No spam. Unsubscribe anytime.
DeKalb County commissioners voted Feb. 17 to authorize a grant-extension letter for the St. Joseph–Spencerville wastewater-treatment project after hearing a construction update from Ben Adams of Commonwealth Engineers.
Adams said construction began in September 2025 and early work included demolition and pile-driving. Unanticipated bad soils beneath the old tanks and extreme winter weather in December and January slowed progress. The contractor provided a recovery schedule and the consulting team expects to finish by August 2026.
Because the original OCCA/OCCRA grant completion timeline was February 2026, Adams asked the board to authorize a letter requesting an extension. Commissioners moved, seconded and approved the extension authorization 3–0. Adams said he would provide the amended letter for signatures and coordinate with county staff.