Committee recommends contract modifications: $266,406.49 for concrete repairs and an exhibit update to United Way allocation
Summary
The finance committee recommended a $266,406.49 modification for Simon Contractors to fix concrete failures on a public-works project and recommended approval of an exhibit revision to an existing $250,000 contract with United Way that reallocates funding among nonprofit partners without increasing the total city contribution.
Get email alerts on the Contract Modifications topic
No spam. Unsubscribe anytime.
The City of Cheyenne finance committee on Feb. 18 recommended two contract modifications:
Adele Bartel, public-works staff engineer, requested contract modification no. 3 to contract 7977 with Simon Contractors for $266,406.49 to address additional concrete repairs after several areas began to fail over three years of work; Bartel said some sidewalk slabs and other sections are cracking and may pose hazards.
Separately, staff presented a modification to contract 7821 with United Way of Laramie County that replaces an exhibit to revise allocations among community nonprofit partners while maintaining the overall contract amount at $250,000; staff said there is no change to the city’s total funding.
Both modifications were moved, seconded and forwarded by the committee as recommendations to the governing body for final approval.