Council hears $1.7M preliminary estimate for Magna Community Center repairs; staff urges quick RFP

Magna City Council · July 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

An agency architect presented a $1.7 million preliminary cost estimate for architectural finishes and MEP upgrades at the Magna Community (Webster) Center; staff recommended issuing an RFP quickly to take advantage of favorable bid conditions and meet contractual turnover obligations.

An agency architect briefed the council on a recently received cost estimate for the Magna Community Center (Webster Center). The consultant’s preliminary estimate allocated about $1,000,000 for architectural finishes and about $700,000 for mechanical, electrical and plumbing systems, for a combined estimate of approximately $1,700,000. Exterior site improvements were mentioned but the detailed breakdown will be provided later.

Staff and council discussed timing. One council member and staff noted construction bid pricing is favorable now and that waiting could increase costs; staff recommended putting the project out to bid quickly and said they might ask the council for direction at the Aug. 26 meeting. Another council member noted the city has contractual obligations related to turnover of the facility and urged timely action.

No binding procurement decision was made at the July 22 meeting; staff indicated they will provide a detailed cost breakdown and potentially bring an RFP authorization request to the Aug. 26 meeting.