County requests $48,340 contract amendment for Fire Station No. 3 waterline work

Dawson County Board of Commissioners · February 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County manager requested a $48,340 amendment to cover additional waterline relocation and pipe extension work after a site reorientation in the Fire Station No. 3 design-build project; funds would come from existing contingency (Spla 6) and Townley Construction is proposed to perform the work.

County Manager Joey Lehi told commissioners on Feb. 19 that a design change requiring reorientation of Fire Station No. 3 moved the mechanical room and utility connections, which in turn required additional vault relocation and extension of…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans