Elementary school addition largely complete; district projects phased through March 2027
Get AI-powered insights, summaries, and transcripts
SubscribeSummary
Project manager Alex Amos told the board that Building E punch-list items are nearly complete, library casework and metal panels are due in early February, site work and landscaping continue and district staff plan phased interior moves and a superintendent/principal walkthrough ahead of final closeout projected around March 1, 2027.
Alex Amos provided the board with a quarterly construction update on the elementary-school addition, describing progress and next steps.
Amos said the addition is already in limited use and that punch-list work for Building E was essentially finished after the holidays. He reported ongoing site work and landscaping, noted metal panels and delayed library casework expected to arrive in early February, and said some interior finishing and casework installation would occur after regular school hours to reduce disruption.
The construction team is coordinating phased work in approximately four-month chunks and will schedule a walkthrough with the administration and the design-construction contractor in February. Amos said the project remains on a timeline that points toward final completion around March 1, 2027 (the presentation described that as roughly 13 months from the current phase). The board and staff also discussed furniture selection (a planned furniture fair to survey teacher and student preferences) and logistics for moving classrooms and storage during the wrap-up phase.
The board thanked construction and school staff for their coordination during holiday moves and for arranging community support to help with the relocation work. The superintendent and building staff said they will continue to update the board monthly as phasing and punch-list items are resolved.