District updates trustees on transportation facility, employee housing and high‑school addition; awards property‑management contract
Summary
Project managers reported winter-related delays but steady progress on the transportation facility with vertical work expected in February; employee housing punch-list work is near complete and deed‑restriction authorization will go to the board in February. The board approved a property‑management contract for district employee housing.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Representatives updated the board Jan. 14 on three capital efforts. Jason Burning provided a construction progress report on the transportation facility, noting that recent heavy rains and frost pushed some work into the winter and currently project teams foresee a four‑to‑six‑week delay; two footing rows have been poured and structural steel is on site, with vertical construction expected in February and delivery of the bus barn projected next fall.
Charlotte Reynolds updated trustees on employee housing: level‑1 punch‑list work is complete, levels 2 and 3 will be worked on in coming weeks, and staff anticipate an early‑spring certificate of occupancy. Reynolds said the board will see deed‑restriction recommendations in February to dedicate the building to workforce housing and that applications for units should be posted in late February or early March.
On the high‑school addition and vestibule, staff said architects are approaching 95% design and that legislative consideration may add funds for design and inflation costs; staff expressed hope the funding would be released upon the governor’s signature. The board also considered property‑management proposals for the district’s 36 employee housing units, received a single proposal from Grand Teton Property Management and approved the award with minor legal modifications.
Trustees asked for timing of a 'topping out' ceremony and asked staff to coordinate notification when milestones are set.