Commissioners reviewed renderings and operational plans for the Washington County Golf Course clubhouse expansion, discussed capacity, rental pricing and a revised June completion date, and received a quarterly financial update showing $2.4 million in revenues vs. a $2.1 million budget; no formal action was taken.
Get email alerts on the Golf Course Expansion topic
No spam. Unsubscribe anytime.
The Washington County Land Use and Planning Commission reviewed plans and renderings for an expansion of the county-owned golf course clubhouse on March 19, hearing details about a new multipurpose room, simulators and an on-site club repair center.
During a presentation, the project representative (Speaker 2) described interior and exterior changes: three entryways into a multipurpose room, large accordion-style sliding window walls to open the room to the patio, a dedicated club repair area moved from the maintenance building into the clubhouse, and two TrackMan simulators intended for player development, lessons and hourly rentals. The presenter said the contractor has poured concrete for basements and a tunnel connecting them and that construction is underway.
Why it matters: Commissioners said the new spaces could broaden community and rental use, support junior and high-school programs and create ancillary revenue through lessons and club sales. The commission asked how the county will balance competitive pricing with recovery of operating costs and staff turnaround time between short rentals.
Capacity, schedule and pricing The presenter said the multipurpose room’s code capacity is 36–37 people; however, when the room is opened to the adjacent spaces and patio the usable capacity will be larger and the presenter said he has asked the Hartford Fire Department to confirm official limits. The bid specified a June 12 completion date; after cold-weather delays and a denied four-to-five-week extension request, the presenter said the contractor’s current completion estimate is around June 19–20, placing the project roughly 10 days behind schedule.
On pricing, the presenter recommended tiered rental rates (resident, nonresident and nonprofit discounts) and described local simulator rental ranges he surveyed ($35 per hour weekdays; about $40–45 on weekends). He also outlined possible memberships and seasonal packages (examples cited included a winter membership model and monthly/hourly access) intended to drive year-round use.
Financial update A financial presenter (Speaker 3) said a written report would be circulated and summarized year-to-date figures: the golf course had about $2.1 million budgeted and roughly $2.4 million in actual revenues — approximately $310,000 above target — while expenses rose as the clubhouse expansion began to draw capital spending into the 2025 accounts. The presenter said pending accounting entries (depreciation and final closeout numbers) will affect the final year-end net and that he will follow up with a breakdown of project-line accounts and contingency usage.
Correction on funding source When one commissioner suggested taxpayer dollars were paying for the expansion, Speaker 3 corrected the record: “There is no taxpayer funding being allocated to this project. It is all coming from the golf course revenues.”
What’s next Staff agreed to circulate more detailed financial breakdowns (authorized budget vs. year-to-date spending and contingency use) and to confirm official occupancy capacities with the fire department. The commission took no motions or votes on the expansion at the meeting and moved on to the golf course quarterly report. The next commission meeting was set for March 19, 2026.
Attributions: Quotations and specific numeric figures are drawn from the presenters and commissioners who spoke during the March 19 meeting; where speakers had no explicit name in the transcript, the article attributes by the speaker label in the record.