DeSoto Parish reviews capital projects: Park Road bid under estimate, central-plant bid exceeds budget
Loading...
Summary
Parish engineering reported multiple capital projects: Merrick LLC was the low bidder on the Park Road/I‑49 Industrial Park project under the engineer's estimate; Stonewall compactor low bid was below estimate; bids for an annex central plant exceeded the jury’s budget and will return for a March budget amendment.
Parish staff updated jurors on several capital and road projects and the status of bids. For Park Road and the I‑49 Industrial Park, the engineer’s estimate was $5,666,000 and the lowest bidder was named as Merrick LLC of Cottonport with a bid of $5,086,269.76; engineering and finance are reviewing the award. For the Stonewall compactor site the engineer’s estimate was $1,943,000 and the low bidder was M and M Builders of Stonewall at $1,548,207.13.
Bids for a new outdoor central plant for the annex building were received; the engineer’s estimate for that plant was $317,750 and the low bid was reported as $515,000 from Blanchard Mechanical Contractors, which exceeds the budget and will require the jury to return in March to consider a budget amendment.
The administrator also provided schedule notes: Nash Road has a pre-bid conference on 03/10/2026 with a bid opening on 03/17/2026 (engineer’s estimate $700,000); the detention facility remains on track for December 2026 completion, with approximately $4,000,000 spent to date of a $26,000,000 budget.
One bid report contained an implausibly large numeric value in the transcript for the LCD Bridal Street project; the record names Apex Construction LLC as the low bidder and lists the engineer’s estimate ($1,586,277), but the numeric bid in the minutes appears to be a transcription error and is not relied on in this report.