Commissioners prioritize capital projects, ask for generator pricing and facility tour
Summary
The county’s capital‑planning committee recommended projects for FY27 including continued EMS building work, a maintenance shop placeholder, library and annex roof work, and investigation of an evidence‑building replacement. Commissioners approved getting price quotes for a community center generator and arranged a facilities tour ahead of budget finalization.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County staff and the capital planning committee presented a draft FY27 capital plan on Feb. 18 that lists near‑term priorities and places for further study. April Snead (county manager) said the committee recommends moving forward on EMS building work, budgeting a placeholder amount for a new maintenance shop, making targeted roof repairs (library, annex), and evaluating the sheriff's evidence‑building which staff said likely needs reskinning or replacement.
Commissioners emphasized getting firm quotes rather than relying on placeholders. They asked for an updated courthouse waterproofing quote and discussed storage and evidence‑building security requirements. The board also directed staff to schedule a facilities tour of the jail, the Dixiguana Road facility and other buildings so commissioners can review conditions before the next budget meeting.
On an emergency‑operations point, commissioners debated identifying a county shelter and whether to equip a community center with a full‑building generator; they approved a motion to obtain generator pricing for one community center and to consider grant possibilities. Staff said a building‑scale generator could cost about $200,000.
What’s next: Staff will gather quotes (roofs, evidence building, generator), pursue available grant funds for feasibility or shelter work, and return with firm numbers for FY27 budget decisions. A site tour was scheduled for the day of the next meeting so commissioners can inspect facilities.