District gives timeline for stadium, HVAC and transportation projects; $5 million appropriation flagged
Summary
Facilities director reported stadium Phase 2 design nearly complete, main‑building renovations at about 60% design, Cottonwood HVAC full replacement slated to start demolition May 23, and officials said a $5 million appropriation is available to support transportation upgrades.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Mister Bartlett, presenting facilities updates, told trustees that the district’s capital program is proceeding on multiple fronts.
He said Phase 2 of the stadium project (design complete) should go to bid as early as next week and that the district is coordinating state and district‑funded items. The main building renovation design team is approximately 60% complete; Bartlett said the project could be ready for bid by June 2026 if milestones hold. He projected occupancy of the new facility in 12 to 15 months, barring unforeseen construction delays.
On the Cottonwood HVAC project, Bartlett described a full HVAC replacement, ceiling grid and tile work, fire suppression upgrades and interior renovations; a pre‑construction meeting was held and demolition was scheduled to begin May 23 with steps to preserve teaching continuity. Bartlett said technology and curriculum materials are being inventoried for removal and temporary storage.
On transportation, Bartlett reported that the joint appropriations committee had approved additional funding and that a $5,000,000 appropriation from 2024 remains available to the district; staff are coordinating timing so major projects do not create local inflationary pressure and are working to ensure bidding schedules do not overlap adversely.
Trustees asked about posting renderings and walk‑through videos; Bartlett said the design team will provide renderings and video and the district planned to publish updates at major design milestones. No board action was taken on these items at the meeting.