Trustees preview six-figure change order request for clubhouse; staff vet contractor claims

Village of Glencoe Board of Trustees · February 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told trustees Change Order No. 2 for the new golf clubhouse bundles owner-initiated revisions, winterization costs and small allowances; the contractor has requested additional funds tied to schedule delays, and trustees said potential additional costs look to be in the six-figure range though exact amounts are under review.

Village staff told trustees that a change order related to the new golf-club clubhouse will appear on the board's upcoming agenda and that negotiations are ongoing with the contractor.

Monica and project staff described Change Order No. 2 with contractor WP Olsen, saying the request covers three primary categories: owner-initiated plan revisions (for example the eastern-drive revision coordinated with neighbors), winterization work not included in the base contract, and a modest allowance (about $15,000) for minor items. Staff said they have compiled backup documentation from subcontractors and are still reconciling some costs.

Trustees acknowledged that permit delays and multiple plan-review cycles contributed to schedule strain. Multiple speakers indicated the eventual additional cost requests are likely a six-figure number (not a seven-figure number) but stressed they are not settled. Trustees said legal counsel and staff are reviewing outstanding contractor claims and noted staff intend to offset unsettled contractor claims where appropriate before approving final payment.

Staff emphasized that the board would see a detailed change-order packet on the Thursday agenda that includes backup and credits from value-engineering decisions. No change order was approved during the meeting; staff asked to proceed with further vetting and to present a reconciled package to the board for action.