Port reports ferry fleet status, FTA-funded landing replacements and Pointe Le Hesse timetable
Loading...
Summary
Staff reported both ferries are running, one vessel remains in dry dock, and the port has secured FTA grants to replace three landing barges; the Pointe Le Hesse replacement is in preliminary engineering with an estimated 2028 construction start and several large cost estimates were presented.
Port staff gave a multi-part status update on ferry operations and port infrastructure, detailing vessel availability, funding and near-term procurement actions.
Staff said both ferries are operating smoothly but noted Belle Chasse 2 remains in dry dock undergoing an extended maintenance period; the port is pursuing schedule details from the contractor and indicated the possibility of using liquidated-damages clauses if timelines are not met. Authority 1 was described as fully complete but temporarily held at the Harvey locks because low river levels prevent transit; Authority 3 had a seawater pump failure and the replacement pump has arrived from Texas.
On procurement, staff identified the diesel-electric ferry as 100% in final design and said the specifications will go out for bid with bids anticipated mid-May. For landings, the port said FTA grant funding covers replacement of three ferry-landing barges (Belle Chasse, Scarsdale and the port security dock) and that engineering for land-based repairs is underway; because estimated construction costs exceed $1,000,000 the work will go to public bid and require appropriate permits.
The Pointe Le Hesse ferry-landing replacement project is in preliminary engineering and survey work; staff said geotechnical and slope-stability surveys have been completed with preliminary construction estimated for 2028. Staff presented several cost figures during the briefing — including an opinion of probable cost cited around $103,000,000 and an $18,600,000 grant amount referenced for the project — and noted that final engineering and grant packaging remain in development.
Commissioners asked technical questions about firefighting pump capacity and vessel firefighting readiness. A staff member estimated the Authority 3 fire pump at roughly 12,000 gallons per minute but cautioned that the number would be confirmed: “Don't quote me on it, but I will get the exact number,” the staff member said. Staff pledged to provide precise specifications to commissioners.
The board discussed continuity-of-service options for aging landing barges, including mud‑jetting and temporary hull patching to maintain service until new barges are built, and approved engineering steps and grant acceptance where required.

