Summary

A presenter recommended replacing the courthouse HVAC with split heat pumps and replacing windows; the presenter cited an estimated capital cost (transcript figure) of about $8,800,000 with a projected 13-year payback and urged budgeting and a professional analysis before bidding.

A courthouse facilities presentation described aging HVAC infrastructure and drafty, single-pane windows. The presenter, identified in the packet as Daryl, said the current system is about 29–30 years old, averages roughly $65,000 a year to operate, and is experiencing frequent breakdowns and high maintenance costs.

Daryl presented a vendor estimate (transcript figure) of about $8,800,000 for a full replacement using split heat pumps that he said would be quieter, more efficient, and reduce ongoing maintenance. He said the system should "pay for itself in about 13 years" and would eliminate propane usage and the need for frequent boiler flushing and cooling-tower replacements.

Commissioners raised concerns about heat-pump performance in cold winter conditions, phased implementation, and construction timelines. One commissioner suggested a professional analysis and going out to bid to ensure the county selects a solution suited to local climate and operations. The presenter suggested doing heating upgrades first and addressing windows later; the court generally agreed to budget for the project and pursue analysis and bids.

What’s next: staff will budget for the project in the coming cycle, solicit a professional energy/facilities analysis and bring options (designs, phasing and estimated schedules) back to the court before issuing a formal request for bids.