Charlotte County: Burnt Store plant CMAR contracted; DEP permit modification expected in October
Summary
Charlotte County Utilities reported the CMAR is under contract for the Burnt Store expansion, staff plans to submit a DEP modification permit in October and will present a fuller timeline July 15; a package plant option could provide 50,000 gpd increments within about four months of contract execution.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Charlotte County Utilities told commissioners on June 19 that the construction manager-at-risk (CMAR) is under contract for the Burnt Store plant expansion and that staff expects to submit a DEP modification permit in October to complete design and obtain estimated construction costs.
Dave Watson, director of Charlotte County Utilities, said staff have been coordinating with the CMAR and regulatory agencies and plan to present a full update and timeline to the board on July 15. Watson also said the utility is operating at roughly 85–90% capacity currently and that connection fees continue to be collected while construction planning proceeds.
Watson said the county is also pursuing a package plant option as a near-term capacity tool. "Depending on the size, we're looking at probably about four months to have that from the time we execute the contract to have it on-site," Watson said, adding that initial package-plant increments could be about 50,000 gallons per day and expandable from there.
Why it matters: The Burnt Store expansion and possible package plant are tied to broader rate and connection-fee discussions because capital allocations and the timing of project costs affect how the county structures fees, debt and the rate path. Staff told commissioners they will include the Burnt Store schedule and cost estimates when they return with the capacity-focused analyses requested by the board.
Ending: Staff will present the full Burnt Store timeline, permitting status and cost estimates at the July 15 Utility Board meeting and will update the board as regulatory milestones are reached.