After arbitration win, Charlotte County seeks FEMA negotiation on Rotunda Bridge repair costs
Summary
The board heard an update on Rotunda Bridge repairs and an engineer's probable cost of about $2.2 million; commissioners voted to send a letter to the county's federal delegation as staff begins negotiations with FEMA to recover eligible repair costs following an arbitration ruling.
Get email alerts on the Rotunda Bridge topic
No spam. Unsubscribe anytime.
Charlotte County's public works director updated commissioners that staff expects to have 100% construction plans and a bid package for the Rotunda Bridge by mid next month and estimated construction duration from an optimistic 10 months to 12—14 months on the long side.
The board also reviewed its recent arbitration outcome with FEMA. While the arbitration found in the county's favor on the question of damage, FEMA did not immediately award monetary damages. John Elias, public works director, and Deputy County Administrator Emily Lewis said staff will begin negotiations with FEMA's new point of contact to press for full repair funding consistent with the court's guidance.
Elias said the engineer's current probable cost estimate for full repair is roughly $2.2 million; commissioners asked for clarity on changes since earlier estimates were lower. Commissioners unanimously approved a motion to send an update letter to the county's federal delegation thanking them for assistance so far and requesting continued engagement during negotiations.
What's next: Staff will finish full plans and return with the contract for construction; FEMA negotiations will proceed in parallel and the county's legislative team will send an update to the federal delegation.