Facilities committee seeks reapproval for partial Radnor Elementary roof replacement
Summary
The Radnor Township SD Facilities Committee heard a staff request to reapprove a partial full-depth roof replacement at Radnor Elementary, covering multiple flat-roof areas plus masonry repairs, power washing and lightning-protection reinstallation; staff said work is planned for summer before students return.
Get email alerts on the Radnor Roof topic
No spam. Unsubscribe anytime.
Radnor Township SD facilities staff on Jan. 13 sought the committee's reapproval to replace multiple flat-roof sections and perform related masonry and waterproofing work at Radnor Elementary School.
The proposal covers full removal of existing roofing down to the structural deck in several flat-roof zones, new insulation, flashing and roofing membrane, repointing and repair of three masonry areas (including pillars and two site walls), power washing and sealing of decorative split-face block beneath windows, and reinstallation and certification testing of roof lightning protection. Staff said the masonry capping will be overlaid with metal to improve water tightness.
Scope, timing and contractor Staff said the work would be performed under the KPN cooperative contract with Weatherproofing Technologies (masonry and related work executed by a different subcontractor but included in the single project scope). Staff emphasized the work is planned for the summer so it can be completed before students return.
Warranty and condition When Lydia Solomon asked when the current roof was last installed, staff said it was installed in 2001 and that the original 15-year warranty has expired; staff described failing vent boots, water infiltration between joints and masonry deterioration as drivers for the work. Asked whether every listed item is strictly necessary, staff said power washing and targeted preventive measures would extend masonry life and reduce later, costlier repairs.
No vote recorded Staff answered committee questions but the transcript contains no recorded final vote or formal approval on the roof project during this meeting. Staff said they plan to return with documentation and permitting information included in the project price.
Next steps Staff will provide detailed cost information and project documents for future committee and board consideration; the Facilities Committee's next meeting was set for Feb. 10.