Board approves several facilities upgrades, tables a dust‑collector change order for clarification
Summary
Solanco SD trustees approved engineering fee increases and a district‑wide alarm/access system (with a 55% PCCD grant application expected), and approved a ballistic‑glass communicator change order. A Smith Middle School dust‑collector change order was tabled while board members requested markup/itemization details.
Get email alerts on the Facilities And Security topic
No spam. Unsubscribe anytime.
The Solanco SD board on Jan. 26 approved multiple facilities and safety items and tabled one contract change order for additional clarification.
Missus Tucker said Moore Engineering submitted an updated MEP (mechanical/electrical/plumbing) fee proposal that added work and $30,000 in fees, bringing the engineering total to $144,900 for the administration office construction project; trustees discussed increased project scope (locker rooms, concession stand, additional bathrooms) and approved the updated proposal.
Tucker also presented a proposal to install alarm and access systems in all district buildings except the high school (which already has installations) at a total project cost of $283,617. Doctor Bliss has applied for a Pennsylvania Commission on Crime and Delinquency (PCCD) school‑safety grant to cover 55% of the cost; Tucker said the hardware cost is $178,000 and the remaining roughly $105,000 covers five‑year licenses. The board approved the proposal by motion.
A Smith Middle School ballistic‑glass communicator insertion (to improve secretary‑to‑visitor audio) was presented at a cost of $3,950, increasing the contract total to $18,345; the board approved the change order.
By contrast, a separate Smith Middle School dust‑collector change order (220 feet of conduit/grounding, $2,988.51, contract cumulative $153,096.51) prompted questions about a 10% markup on materials and labor. Trustees requested an itemized breakdown and voted to table the change order for clarification.