Board approves field-turf change order; bond team flags Phase 2 elementary cost pressures

Oregon City School District Board of Education · October 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a change order (Resolution 2526-226) to add a 6% cement mixture to outdoor fields to allow wet-season work; staff said the work fits the $12 million fields-and-grounds budget but Phase 2 elementary cost estimates are over budget and value-engineering is under way.

The school board voted to approve a change order for field work at Oregon City High School and received an update showing both progress and cost pressures on the district pos;s bond program.

David Hobbs reviewed field construction work and explained that stormwater retention and underground "R tank" installations are underway; he said turf remains the final installation step. Hobbs said crews have encountered large boulders in excavations — an unforeseen condition that may generate change orders — and that the project team is working through those issues with contractors.

The board then considered a recommended change order for Filter Field Turf USA Inc. to add a cement mixture to field surfaces to permit work during wet weather. Hobbs described the mixture as a 6% cement blend and said the cost was anticipated and included in the fields-and-grounds line of the bond ("we have a $12,000,000 budget for the fields and grounds across the district, and this falls within that budget").

Vice Chair Controlla moved the resolution (identified in the meeting as 2526-226); the board seconded and approved the measure by roll-call vote.

Hobbs also noted that CM/GC cost estimates for Phase 2 elementary schools are currently over budget; the design team has paused while value-engineering options are explored. He said the CTE high-school program is tracking on budget and that additional community design sessions and a bond work session are planned in late October and early December.