Navajo County board approves materials contract for 2-mile road segment serving Navajo Nation route

Navajo County Board of Supervisors · December 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a materials-only contract for aggregate base material to improve about 2 miles of Navajo Nation Route N 9009806 in District 2, after staff reported two bids and recommended the apparent low bidder, Brimhall. Staff said the Division of Transportation will place the material; contract details are in the board packet.

The Navajo County Board of Supervisors voted to award a materials-only contract for aggregate base material to improve about 2 miles of Navajo Nation Route N 9009806 in District 2.

Manny, a public works staff member, told the board the procurement was split out as a materials-only contract because the estimated material cost exceeded $100,000. He said the county advertised the materials-only solicitation, opened bids on Nov. 13, and received two bids. Manny said Brimhall was the apparent low bidder and staff recommended awarding the contract to that bidder; the Navajo Division of Transportation will perform placement of the material on the route.

A supervisor who spoke in support noted the project began under a predecessor in 2018 and emphasized benefits for high-risk residents and students who use the road to reach Holbrook Unified School District and Delcon Community School. The supervisor moved to approve the contract; the motion was seconded and passed unanimously.

The staff presentation referenced contract pricing and details in the meeting packet; the county did not announce a final dollar amount on the public record during the meeting. The motion and vote were procedural: the board approved the award and the chair declared the motion passed.

Next steps identified in the discussion included proceeding with contract award and coordinating with the Navajo Division of Transportation for material placement. Board members did not state a specific timetable during the public session.