Citizen Portal
Sign In

Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows

Takoma Park council hears updated Metropolitan Branch Trail design; city-sized segment budgeted at $1.8 million

Takoma Park City Council · September 24, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City planners and RK&K presented an updated design to widen Takoma Park’s section of the Metropolitan Branch Trail to 10–11 feet with continuous pedestrian lighting, updated crossings, stormwater treatment and reduced tree impacts; estimated construction cost for the city segment is about $1.8 million.

Transit planner Kasey Ann Spence and consultant Emily Martin (RK&K) presented updated plans for Takoma Park’s portion of the Metropolitan Branch Trail, outlining a design that widens the existing path, adds continuous pedestrian-scale lighting and wayfinding signage, and improves crossings at Buffalo/Tacoma and Fenton/Tacoma.

The project limits run from the Eastern/Tacoma intersection, parallel Tacoma Avenue to Fenton Street, and continue up to the Montgomery College pedestrian overpass. The plan calls for an 11-foot (typical) trail section where feasible and a 3–4 foot buffer from traffic where possible to meet county breezeway standards and support side-by-side cycling and safe passing.

Consultants and staff described design trade-offs driven by the adjacent CSX right-of-way, which constrains widening in several locations. The presentation noted tree impacts identified in the 30% design were reduced roughly 12 percent through alignment adjustments (raising the trail profile, symmetric spur widening, relocating lighting to the CSX side) and tree-protection techniques such as root pruning and air spading.

An urban-forest accounting distinction emerged during Q&A: the consultant’s total tree-impact count (including small landscape and invasive specimens) was 130, while the city’s count of protected urban-forest trees to be removed is 66 (60 of those are 0–20 inch caliper; six are 20–40 inch caliper). Staff estimated tree-removal fees at about $42,000; officials said the precise fee allocation is still being finalized.

The plan includes on-site stormwater treatment measures (including permeable pavement within some existing parking spaces) intended to manage runoff without taking additional right-of-way. Presenters said long corridor lighting is a major cost driver alongside asphalt and earthwork; the current estimated construction cost for Takoma Park’s segment is about $1,800,000. Staff said the 60% design will be submitted next month, with 95% and final plans expected in early 2026, and that the city is continuing to pursue construction funding.

Councilmembers asked about light clearance for taller cyclists, historical-marker signage language (the sign will be relocated within project limits and the verbiage can be revisited), native planting and long-term maintenance, and how tree roots and pavement will coexist. Staff said the lighting will meet pedestrian-scale height requirements, sign wording can be subject to community review, native-planting choices will be vetted with Public Works, and the design uses raised profile and repaving as maintenance strategies where roots affect pavement.

Next steps include submission of 60% design plans, further coordination with CSX and Montgomery County, and continued community engagement as the city secures construction funding.