Committee approves bundled change orders, early electrical GMPs and moves to award construction manager

Building Committee (school construction program) · January 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Members approved a bundled set of project change orders, voted to approve early electrical GMPs for two schools, and—after an executive session—voted to award a construction-manager contract to O&G Construction; committee asked staff to provide a detailed allowance/contingency breakdown.

The building committee approved a series of project change orders (PCOs) across Stanton, Greenville and Stan projects, approved early electrical Guaranteed Maximum Price (GMP) packages for two schools, and—after a closed executive session—moved to award a construction-manager contract to O&G Construction.

Consent and PCO approvals: The chair moved and the committee approved a bundled batch of PCOs for Stanton (including PCO 16, PCR/PR line items, credits and contingency-funded items). Staff explained which line items are drawn from GMP allowances and which are charged to the construction contingency; examples discussed included a $27,465.90 credit for additional pre-blast surveys (PCO 16) and a revised fencing cost (noted in the discussion as $65,094 following negotiation). Committee members requested and the chair agreed to circulate a full breakdown of allowance usage and contingency balances after the meeting.

GMP approvals: The committee considered and approved two separate early-electrical GMPs presented as phase-1 procurement packages. The staff summary described exhibit A-1 cost breakdowns (trade contract amounts, a $20,000 allowance for potential changes, general conditions, a 2.5% contingency, bonds/insurance and fee). The office/elementary package GMP was stated in the briefing as $492,137 for the office package (presented as a phase-1 GMP figure); the Moriarty GMP figure was presented separately in the backup exhibit.

Award of construction-manager contract: After entering executive session to discuss selection criteria for the construction manager, the committee returned to public session and a motion was made to award a contract to O&G Construction. The recorded outcome in the transcript shows eight affirmatives and one abstention (one committee member was not responding when votes were recorded). The chair confirmed the motion carried.

Votes at a glance - Approval of minutes and consent agenda: motion carried (roll call recorded; no recorded dissent). - Batch PCO approvals for Stanton (PCO 16, 24, 27, 34, 23 r1, 24 r1 25, 26, 29, 30, 31, 32, 33, 34, 35, 37, 38, 39, 40, 41, 42, 43, 44, 45): motion carried (roll call recorded). - GMP approval — UNKUS (early electrical phase 1): motion carried (roll call recorded). - GMP approval — Moriarty (early electrical phase 1): motion carried (roll call recorded). - Award contract to O&G Construction (post-executive session): motion carried; recorded tally shows 8 yes, 0 no, 1 abstain/absent at the time of recording.

The committee asked staff for follow-up financial detail on allowances and contingency balances. No litigation or legal authority changes were made during the meeting.

The meeting then adjourned.