Grants Pass council approves Amendment 13 to water-treatment project, adds roughly $9.19 million and 28 days to contract

Grants Pass City Council · February 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city approved a resolution authorizing the city manager to sign Amendment 13 with Slayton Constructors for intake and raw-water pump-station work on the replacement water treatment plant; staff said the amendment adds about $9.19 million and 28 days to the contract and that funds are budgeted within the project.

Grants Pass City Council on Feb. 18 approved a resolution authorizing the city manager to sign Amendment 13 to the design‑build agreement with Slayton Constructors for intake and raw‑water pump‑station modifications to the replacement water treatment plant.

City staff presented the amendment as the final modification needed for the intake construction after hydraulic flow issues were identified in detailed design work. Jason, the presenting city staff member, said the amendment’s cost was $9,185,938 and that the change would add 28 days to the contract…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans