Stark County Parks director reports $417,000 in 2025 receipts, seeks staged work on campground electrical project

Stark County Board of Commissioners · February 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The parks director told commissioners 2025 receipts were about $417,000 and that Bass Lake Campground generated roughly $172,000. She said the campground electrical RFP attracted limited bids and that she’ll return with additional quotes; commissioners encouraged staging the work and exploring options to move the project forward.

Amy (Speaker 13), representing Stark County Parks, presented the department’s annual fiscal report. She said total 2025 receipts were approximately $417,000 — about $100,000 more than the prior year — with the Bass Lake Campground contributing roughly $172,000 and beach/piers revenue about $86,000. Amy outlined seven parks and launches the department manages and described capital projects funded in part by a Land and Water Conservation Fund (LWCF) grant with a county match.

On the campground electrical upgrade, Amy said she had solicited five electricians but only one submitted a formal bid; others said they needed an RFP to bid. Commissioners suggested breaking the project into stages and exploring more procurement options. Amy said she would return with additional quotes and a phased plan, and the board encouraged her to keep moving forward.

Amy also said the parks department is financially self‑sustaining through operations and fundraising since a $20,000 county stipend ended in 2023. Commissioners thanked the parks staff and asked for a follow‑up on fundraising splits and remaining grant balances.

Why it matters: Parks revenue helps fund operations and local recreation. The campground electrical project affects visitor services and seasonal operations; getting multiple bids or staging work could reduce costs and avoid delays.

Next steps: Parks staff will pursue additional bids or staged procurement and return with an updated schedule and cost breakdown for the electrical work.