Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

LCRA TSC approves three capital projects including new 138 kV substation and broadband easement amendments

LCRA Transmission Services Corporation Board of Directors · February 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved three projects: a La Sima 138 kV substation (est. $16.4M, completion Dec. 31, 2026), a Sakset substation upgrade (est. $18.8M, completion Dec. 31, 2026), and a broadband easement enhancement to amend rights on about 540 parcels (est. $7.5M, completion Dec. 31, 2027), funded in part by Texas Broadband grant funds.

The LCRA Transmission Services Corporation board on Feb. 18 approved three capital projects presented by staff.

Josh Cole described the La Sima Substation addition, a new 138‑kilovolt substation to create a point of interconnection to serve Pedernales Electric Cooperative near Ranch Road 12 west of San Marcos. The project’s recommended completion date is Dec. 31, 2026, at an estimated…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans