Summary

Public Works said chip‑seal work is about 64% complete and that crews are addressing Tonopah, Beatty and Pahrump projects while budget limits constrain responses to >1,000 requests; residents urged faster pothole and striping repairs and asked about a possible tax to fund roads.

Nye County Public Works updated the Board Oct. 1 on road maintenance and chip‑seal operations. Assistant director reported about 64% of this year’s chip‑seal goal is complete, with Tonopah and Beatty work finishing soon and about 13 miles left in Pahrump for service treatments. Staff said crews have processed roughly 1,000 maintenance requests since January and completed about 330.

Public commenters from Pahrump and Amargosa described severely damaged local roads — including Bridal and Atomic roads — and urged prioritization, restriping and pothole repairs; one resident said gravel and tank‑trap conditions are causing vehicle damage. Public Works acknowledged budget constraints: fiscal year 2024 funds are nearly expended and staff said they are implementing a new work‑order system to go live Jan. 1 to provide status updates to residents.

Commissioners discussed long‑term funding and noted a quarter‑percent sales tax question on the ballot that could fund roads; staff said some grant funding is being pursued for specific projects but that many roads will require base repairs not covered by short‑term resurfacing.

Next steps: Public Works will continue chip‑seal operations, implement the new work‑order system, and return with more detailed lists of upcoming road treatments and grant prospects.