Board approves amendment for Plumas Lake SR‑70 interchange design; staff say roundabouts could save up to $13 million

Yuba County Board of Supervisors · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County public works presented an amendment to the Plumas Lake Boulevard/SR‑70 interchange design that proposes two roundabouts to reduce bridge and right‑of‑way costs; staff estimated up to $13 million in potential savings and the board approved the amendment.

Public Works described proposed value‑engineering changes to the Plumas Lake Boulevard/SR‑70 interchange (Phase 2) and requested approval of Amendment No. 3 to the agreement with Wood Rogers, Inc.

Sam Button said the project already has $35 million in federal construction funding and that a conceptual redesign moving the alignment slightly north and using two roundabouts could significantly reduce the size and cost of a railroad bridge, reduce right‑of‑way impacts (potentially saving several acres of rice land) and lower combined roadway and bridge expenses by an estimated up to $13 million. He noted the amendment increases design and retaining‑wall costs by roughly $3.6 million but could yield the larger estimated savings during construction.

Supervisors thanked staff and the consultant for identifying cost‑saving opportunities; the board approved the amendment by voice vote.

Next steps: staff will continue design work and refine property‑acquisition estimates; construction was described as targeted for 2026 or 2027 pending design and funding schedules.