Council awards $2.636 million contract to rebuild North Dakota Street with storm sewer and bike trail
Summary
Council approved a $2,636,001.34 contract to Reedy Construction for reconstruction of North Dakota Street north of Fairgrounds Road, including storm sewer and a bike trail; staff said work will start this summer and was enabled by a county boundary-line highway agreement.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Aberdeen City Council voted to award the North Dakota Street reconstruction contract to Reedy Construction for $2,636,001.34.
Dustin (staff) said the project will reconstruct Dakota Street north of Fairgrounds Road into an urban section, including storm sewer and a bike trail. He said two bids were received, prices were competitive, and Reedy Construction—having completed a similar section before—was the recommended low bidder.
Council members noted the project was enabled by a boundary-line highway agreement with the county negotiated last summer that clarified maintenance responsibilities and charged partners appropriately. Staff said the project is expected to proceed this summer.
Council approved the motion to accept the bid and move forward with contract award. No substantive public opposition or requested amendments were recorded during the meeting.