Pharr bridge expansion on track; border inspection facility to open March 1

Foreign International Bridge Board · February 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineer reported construction progress on dock expansion, ag lab and international span with a July 2026 completion estimate for the bridge expansion; officials said the previously idle border safety inspection facility will open March 1 and HAZMAT training is scheduled Feb. 26.

Patricia Longoria, the city engineer, told the board the dock expansion was about 63% complete, the agricultural laboratory roughly 40% complete and the international bridge expansion was "108% on time," with an estimated completion date in July 2026. She flagged relocation of irrigation-district pumps as a current schedule driver and said the crossover work was complete, with a crane set to place the international span…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans