Pharr bridge expansion on track; border inspection facility to open March 1
Summary
City engineer reported construction progress on dock expansion, ag lab and international span with a July 2026 completion estimate for the bridge expansion; officials said the previously idle border safety inspection facility will open March 1 and HAZMAT training is scheduled Feb. 26.
Patricia Longoria, the city engineer, told the board the dock expansion was about 63% complete, the agricultural laboratory roughly 40% complete and the international bridge expansion was "108% on time," with an estimated completion date in July 2026. She flagged relocation of irrigation-district pumps as a current schedule driver and said the crossover work was complete, with a crane set to place the international span…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat