Panama City accepts $1.5M state grant boost for Pretty Bayou sewer project, approves CEI contract amendment

City of Panama City Commission · February 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City commissioners approved a $1.5 million increase from FDEP for the Pretty Bayou/Kings Point septic-to-sewer Phase 3 project (no local match), raising the grant to $8,499,520, and authorized a $230,000 amendment for Panhandle Engineering's CEI services; both measures passed unanimously.

Panama City’s Commission voted Feb. 24 to accept a $1.5 million increase in state grant funding for the Pretty Bayou/Kings Point septic-to-sewer Phase 3 project and approved a related professional-services amendment for construction engineering and inspection (CEI).

City staff said Amendment No. 6 to the existing subrecipient agreement with the Florida Department of Environmental Protection adds $1,500,000 with no city match, increasing the total grant to $8,499,520. Staff described Phase 3 as including roughly 16,000 linear feet of low-pressure sewer, about 15,400 linear feet of potable water main tie-ins, and installation of 35 additional fire hydrants to improve service and fire coverage in multiple neighborhoods.

"Amendment number 6 adds $1,500,000.00 to the agreement with no match from the city, increasing the total grant amount to $8,499,520.00," a staff presenter stated while summarizing the funding and project scope.

The commission also approved Panhandle Engineering Amendment No. 7 to Task Order 13067, authorizing up to $230,000 for CEI services and raising the task order total to $1,381,320. Staff said the amendment will allow Panhandle to provide 30% design-level planning, construction management and on-site inspection services necessary to advance Phase 3 to bid and construction.

Both votes passed 4-0. Staff said they will advertise for bids and proceed with procurement steps upon completion of required design and CEI scopes.