At its Dec. 16 meeting the council approved Resolution 684 creating a new service area, awarded a litter-removal contract to SVS Groundworks, confirmed interim grant polls including an $80,000 DNR application, approved two US DOT bridge engineering grant applications, renewed an airport lease with GeForce Avionics LLC and authorized an RFP for lobbying services; most motions passed unanimously.
Get email alerts on the Meeting Votes topic
No spam. Unsubscribe anytime.
The Dorchester County Council on Dec. 16 approved several agenda items and formal actions, including a resolution to establish a new service area, multiple grant submissions, a solid-waste contract award and a 10-year airport lease.
Resolution 684: new service area. The council held a public hearing on Resolution 684 to create a new service area described in the transcript as 'McEwen Point section 1' (also referenced in the hearing record as 'McKeel Point'/'McKeel 0.1'). Sharon Smith of the City of Cambridge asked whether the city’s wastewater system had capacity to accept additional flows given recent pump-station issues. County staff reported a prior memorandum of understanding (MOU) and said the wastewater treatment plant had adequate overall capacity to accept the additional properties identified; staff distinguished localized pump-station issues (e.g., Water Street) from overall plant capacity. The council voted in roll call: Councilman Travers — Yes; Councilman Detmer — Yes; Councilman Kramer — Yes; Councilman Nichols — Yes; Presiding official — Yes. The resolution passed unanimously.
Solid-waste contract award. John Cooney, the county’s solid-waste manager, recommended awarding the litter-removal services contract to the lowest bidder. Council discussion focused on staffing levels and the manager’s discretion to call crews on a will-call basis; the county noted detainee labor from the corrections center has not been available in sufficient numbers. The contract was awarded to SVS Groundworks at a daily rate of $600 for two laborers; the motion passed.
Interim polls confirmed. Councilors confirmed two interim poll actions taken between meetings: a requested increase of $185,000 to an LGIM grant application (which raised the county match by $9,758) and submission of an $80,000 resiliency-through-restoration grant application to the Maryland Department of Natural Resources for Elliott Island shoreline protection; both confirmations were approved by the council.
US DOT bridge engineering grants. The council approved submission of two US Department of Transportation grant applications to fund 100% of engineering costs for bridge maintenance projects: Hoopers Island ($686,925) and Shorter/Shorters Works ($565,670). The projects were moved, seconded and approved.
Airport lease. Airport director Steve Newer presented a proposed lease with GeForce Avionics LLC for the South anchor at the Cambridge Dorchester Regional Airport: total rent of $229,736 for the initial 10-year term, a 3% annual escalation and three additional optional five-year renewal terms. The council approved proceeding with the lease.
Committee appointment and RFP. The council filled a vacancy on the agriculture reconciliation committee with Mike Knauer (nominated by the local farm bureau) and voted unanimously to issue a request for proposals (RFP) seeking lobbying services for the county; councilors said finalists would be interviewed if needed.
Audit and bond-rating timeline. Staff announced the county’s FY2023 audit has been posted to the county website. Staff also said the county previously suffered a cyber incident that required destruction of 24 servers and migration to a new accounting system; council and staff said they will seek to bring the county back to bond-rating agencies after completing required FY24/FY25 reporting.
Public comment. Comments included thanks to the county for recreation support and questions about the audit and bond-rating process; staff answered that bond-rating outreach will follow completion of the next two years of audited reporting.