Council awards $2.5M wastewater contract, selects AD Morgan CMAR and approves $4.76M indoor tennis GMP; dais AV upgrade also approved

Zephyrhills City Council · August 27, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved multiple capital and procurement items: award to RCM Utilities for wastewater pump station rehab (~$2.50M), selected AD Morgan as CMAR for the city yard design phase, approved an indoor tennis facility GMP (~$4.76M), and authorized dais/AV improvements including an optional ballistic panel add-on.

Council approved several procurement and capital items that move projects toward construction.

Wastewater pump station: Staff recommended accepting the low bid from RCM Utilities to rehabilitate the wastewater effluent pump station and associated chlorine contact basins; the low bid (including contingency) was $2,501,367.30 and council approved awarding the contract.

Construction manager at risk (city yard complex): Council authorized a CMAR agreement (preconstruction/design phase) with AD Morgan Corporation. The preconstruction design services expense was cited at 0.75% (about $120,000) and staff said the agreement allows the city to terminate if it chooses not to proceed to construction.

Indoor tennis facility GMP: Council approved a guaranteed maximum price for the indoor tennis facility and outdoor courts not to exceed $4,755,576.36. Council discussed mezzanine/storage options and the HVAC/ceiling design for finished spaces; public works director Shane LeBlanc noted that finished spaces will have hard ceilings and ductwork and that the team is working to include mezzanine storage in the GMP price where feasible.

City council dais and AV upgrades: Staff proposed raising and reconfiguring the dais, adding AV hardwiring and an alternate ballistic-panel option. The base task order was $97,383.30 with the ballistic-panel alternate quoted at $19,131.25 for a project total of $116,514.55 if the alternate is selected. Council approved the project and staff said the goal is to complete the work around the turn of the year.

Quotes and timeline: "All of the finished condition spaces will have a hard ceiling and the ductwork," Public Works Director Shane LeBlanc said when describing mechanical design for the tennis facility. Staff emphasized schedule constraints on the tennis facility procurement to meet a June 30, 2025 completion date.

What’s next: Staff will finalize contracts with RCM Utilities and AD Morgan, issue the GMP agreement for the tennis facility, and schedule project kickoff and procurement steps for the dais and AV upgrades.