Village presents annual stormwater report, highlights Sawmill River cleanup and sampling needs
Summary
Village staff presented an 18-page, New York State DEC-required stormwater program report summarizing six program elements, noting most runoff flows to the Sawmill River and identifying increased sampling, mapping and training needs to address impaired Bronx River outfalls.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
An unidentified village staff member presented the village's annual stormwater program report to the board, describing the six-part, state-mandated program and steps the village is taking to maintain compliance with New York State Department of Environmental Conservation requirements. The presenter said the 18-page report outlines current activities and planned work and will be posted on the village website when it is finalized.
The staff member said the program covers public outreach and involvement, construction-site runoff controls, post-construction stormwater management, pollution prevention and internal good-housekeeping for departments such as public works and water. He said about 80% of the village's stormwater drains to the Sawmill River and about 20% drains through Manhattan Park toward the Bronx River, which he described as "a little more, delicate" and noted as an impaired water body. The report emphasizes annual maintenance and inspection of post-construction filtration systems, more extensive employee training, improved system mapping and increased water sampling at outfalls to check for illicit discharges and contaminants.
"This 18 page report ... talks about how we're in compliance and everything we're doing and going forward," the presenter said, adding the village will record the meeting date for state reporting and post the final report publicly. The board did not take a formal vote on the report during the discussion; the presentation was followed by routine agenda items.
The presentation highlighted the Sawmill River cleanup event scheduled for "the 20 sixth," which staff said has drawn strong volunteer participation in prior years and serves both cleanup and education goals for children and community volunteers. The village will continue to coordinate outreach and sampling work tied to the DEC reporting schedule.
The village identified next steps including expanded sampling at outfalls that discharge to impaired waters, ongoing mapping of the stormwater system and additional employee training over the coming five years.