Town of Farmington reviews construction closeout, approves 11 change orders and finalizes move plan
Summary
Town staff reported that the new town hall project is nearing completion, with KBE’s contract increased to $13,315,962 after approved change orders and about $44,000 remaining in contingency; staff expect bulk moves over Presidents' Day weekend and aim to be fully moved in by March 1.
The Town of Farmington met to review construction closeout details for the new town hall, approve a package of change orders and outline a phased move plan. Town staff said contracted work is nearly finished and the elevator and state inspections are the final approvals before occupancy.
Town staff presented updated financials and change orders tied to the project. Speaker 7 said the original KBE contract was $12,775,000 and that authorized change orders have increased KBE’s contract amount to $13,315,962; he added that the owner’s contingency is about $44,000 remaining. "So with all of those, the change orders plus the forecasted, we have, just over $44,000 left in the contingency, but we are at the end of the project," Speaker 7 said.
Staff reviewed 11 change orders (COR…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat