Town manager seeks board consideration of $18,000 change order for Spencer Town park

Spencer Town Board of Aldermen · December 6, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town manager asked the board to add an $18,000 change order to the regular agenda to split a storage room into two to meet county building codes; the project has a $50,000 contingency and would leave about $30,000 remaining if approved.

The Spencer Town manager presented an add‑on item at the Dec. 5 pre‑agenda meeting asking the Board of Aldermen to consider a change order of about $18,000 to the town park project to meet county plan‑review requirements.

The manager said the plan review identified the need to separate a single large storage room into two rooms so fountain equipment, chemicals and related systems are in a separate storeroom, triggering masonry, HVAC and electrical work. The manager said he has delegated authority for change orders under $10,000 but this item exceeds that limit, so board consideration is required. “This 1 is a change order to the tune of $18,000,” he said.

Project finances: the manager said the project has a $50,000 contingency and that previous changes resulted in a net change of only about $1,200; approving the $18,000 change order would leave “about over $30,000 left in contingency,” he stated.

Board handling: the manager suggested the item could go on the consent agenda if members were comfortable, but several members said they would prefer a brief explanation on the regular meeting agenda to highlight where park funding (fundraisers, grants, donations) came from; the chair directed staff to add the change order as item 10 on the Dec. 10 agenda.

What’s next: The board added the change order to the Dec. 10 regular agenda; no final approval of the change order was recorded at the pre‑agenda meeting.