Mobile County Public Schools reviews broad consent agenda including $2.1M IDEA flow-through contract and generator replacements
Summary
At a work session, staff presented a large consent agenda covering policy alignment, multiple contracts (including a $2,135,039.22 agreement tied to IDEA/flow-through funds), professional development services, generator replacement bids, leases, and a request by Alabama Power to use Ladd Stadium as a staging area; the board did not vote on these items at the work session.
Get email alerts on the Consent Agenda Contracts topic
No spam. Unsubscribe anytime.
Unidentified Speaker 4 led a review of action items and a lengthy consent agenda at the Mobile County Public Schools work session, highlighting multiple contracts, funding sources, and facility items that staff plan to bundle for board consideration.
Key items presented: Unidentified Speaker 4 said Action Item C1 adopted calendar Option 1 (first day Aug. 10, last day May 26). A major contract (C3) described as Learning Tree with the Alabama Department of Education would provide services tied to IDEA/flow-through funds at $2,135,039.22. Other notable items included HMH Center for Model Schools (phase 1 leadership coaching, $441,936, RAISE Act funds), a Renaissance Learning one-year license ($345,689.12, district local funds), progress learning subscription ($218,949.12, local funds), and multiple Title I and school-improvement professional-development vendors.
Facilities and vendor decisions: Speaker 4 reported generator replacement bids: Theodore High School accepted the lowest bid from Rochere Electric for $159,500 (coming from A and T funds) and Baker High School contract to Bagby and Russell for $103,700. Several smaller contracts were listed, from translation services not to exceed $50,000 to software licenses and program fees. The board also heard staff describe 11 farming/grazing lease renewals totaling $74,661.46 and a five-year lease with Moss Hills Sportsman Club for $17,047.58.
Alabama Power request and easement: Unidentified Speaker 4 said Alabama Power requested temporary use of Ladd Stadium parking as a staging area to support power-restoration efforts after hurricanes or storms; the district would not receive payment for that use. Board members asked whether the company would need to use district power or could plug in equipment and suggested adding stipulations; staff said they would "take a look" and check details. Speaker 4 also introduced an easement (C37) to Alabama Power for installation and maintenance of electrical lines; no financial exchange was noted.
Process and next steps: Unidentified Speaker 4 moved the consent agenda forward and asked for questions; the items will be included in the upcoming board meeting consent package (D1–D22) for formal approval. Personnel items and student expulsions were listed under separate cover; informational items include monthly financials and purchase orders over $5,000. The work session ended after a motion to adjourn carried; no formal votes on the listed contracts were recorded in this transcript.
Ending: Staff will add a few budget amendments and facility items to the Wednesday board meeting package for formal action.