Rutherford County forensic center near completion; contingency and VE items detailed
Summary
County staff and contractors told the Property Management Committee the Rutherford County Regional Forensic Center site work is about 80% complete, interior mechanical work about 75% complete, and the project has a $457,000 design/construction contingency after three value‑engineering items were added back into scope.
The Rutherford County Property Management Committee received a detailed construction update on the Rutherford County Regional Forensic Center, with county and contractor representatives reporting steady progress and a remaining design/construction contingency.
Adam Dodd, director of facilities maintenance, told the committee that "the overall site work remains at approximately 80% complete," with stormwater and retention ponds at about 90%, exterior sheathing and the roof substantially finished, and interior mechanical, plumbing and electrical rough‑in…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat