Public works seeks contract adjustments, extra days as sewer and resurfacing work progresses
Summary
Staff reported manhole rehab vs replacement decisions, awarded 70 extra construction days for sewer work, and recommended increasing the resurfacing contract by up to 50% to sustain work under the $15,000,000 bond; contingency funds were said to be insufficient to cover the change orders.
Public‑works staff provided an update on road resurfacing and sewer work at the Oct. 6 council work session, outlining reasons for change orders and schedule adjustments.
Staff said sewer work is approximately 9–10% complete and that crews have completed manhole rehabilitation or replacement in several locations. Based…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat