Tempe previews nearly $2 billion in five-year capital requests, flags bond and staffing constraints
Summary
Municipal Budget Director Robert Baer presented a first look at the five-year Capital Improvement Program, noting departments submitted nearly $2,000,000,000 in requests and staff will evaluate bond capacity, cash funding, and organizational capacity before recommended projects are presented in March.
Get email alerts on the Capital Planning topic
No spam. Unsubscribe anytime.
Municipal Budget Director Robert Baer told the Tempe City Council that departments have submitted nearly $2 billion in project requests for the five-year Capital Improvement Program and that staff will prioritize projects based on funding availability and organizational capacity.
Baer emphasized the CIP is a planning document: only the first year is adopted, but the five-year plan helps council and residents see long-term capital needs. He walked the council through the packet layout, which includes program summaries, funding-source breakdowns and project detail pages showing descriptions, estimated budgets and operating impacts.
Staff identified key constraints that will shape recommendations: legal limits on property-tax growth tied to general obligation bond capacity, debt and coverage ratios needed to preserve bond ratings, available cash across special revenue and enterprise funds, and whether city engineering, procurement and finance staffing can support project delivery. Baer said a cross-departmental team will score and prioritize CIP projects and that initial recommended capital projects will be presented on March 23.
No formal approvals were requested at the work study session; the presentation served to familiarize council and the public with the proposed projects and the tradeoffs staff will consider when assembling a final recommended CIP for council review.