EDC reports: Harris Street contractor terminated; downtown drainage and gateway sign move forward
Summary
EDC director reported termination of DG Medina’s Harris Street contract, Cedros Paving completed deficiencies, staff expect a construction award by April for revised plans with NTP in May and completion late in the year; downtown drainage NTP anticipated by month-end and a gateway sign bidding process is being prepared.
At the Feb. 9 meeting, Speaker 7, presenting the economic-development report, outlined several project updates and timelines.
Harris Street: Speaker 7 said the DG Medina contract for Harris Street “was terminated by convenience on December 5.” DG Medina remobilized by Jan. 10; Cedros Paving completed deficiency items including a concrete apron at FM 1093, resealing of expansion joints and installation of a storm inlet in phase 1. Staff…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat