EDC reports: Harris Street contractor terminated; downtown drainage and gateway sign move forward

Forster Development Corporation (Fulshear Economic Development Corporation) · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

EDC director reported termination of DG Medina’s Harris Street contract, Cedros Paving completed deficiencies, staff expect a construction award by April for revised plans with NTP in May and completion late in the year; downtown drainage NTP anticipated by month-end and a gateway sign bidding process is being prepared.

At the Feb. 9 meeting, Speaker 7, presenting the economic-development report, outlined several project updates and timelines.

Harris Street: Speaker 7 said the DG Medina contract for Harris Street “was terminated by convenience on December 5.” DG Medina remobilized by Jan. 10; Cedros Paving completed deficiency items including a concrete apron at FM 1093, resealing of expansion joints and installation of a storm inlet in phase 1. Staff are finalizing a notice to proceed for Silver Sands to complete landscaping and irrigation for phase 1. Speaker 7 said EmbiCo will finalize revised plans by the 13th, staff will resolicit by the end of the month, and they hope to award a new construction contract by April with an anticipated notice to proceed in May and an estimated completion in November or December of the year.

Final payments and payouts: Speaker 7 said DG Medina submitted a final payout that staff are reviewing and “most likely going to reject based on the amount.” Cedros’ portion has been paid.

Downtown East Side / 4th Street drainage: Speaker 7 reported the contractor has ordered storm-sewer boxes and staff anticipate issuing a notice to proceed by the end of the month; work is on hold until materials arrive on site.

Gateway sign and business outreach: Staff reported they are moving the gateway sign project into the bidding process and are coordinating questions with KJ DeForest. Staff also said they (Speaker 2 and Speaker 7) will attend the ICSC conference next week.

What’s next

Staff will bring revised plans and a solicitation schedule back to the board and will report on any disputed final payout from DG Medina. Executive-session matters related to property values were discussed in closed session and no action was taken in open session.