Bowie council approves $68,640 to install temporary Rayburn Street water line after repeated breaks

Bowie City Council · March 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved $68,640 from the infrastructure fund to pay contractors to install a temporary above-ground water line on Rayburn Street after the existing line broke multiple times; the job was estimated at roughly $40 per foot for 1,720 feet and will serve about 15 houses.

Council authorized $68,640 from the city's infrastructure fund to install a temporary water line on Rayburn Street after contractors repeatedly broke the existing buried line during sewer work.

Tony (city speaker) described the issue: the sewer work had caused three breaks in the water line serving about 15 houses, so staff and a contractor proposed installing a temporary above-ground line while sewer repairs continue. He presented the estimate: a contractor bid $52,640 and supplies totaled about $16,000, for a $68,640 request. Tony said, "So I ask for y'all to approve $68,640 out of the infrastructure fund to pay these contractors to lay that loan." He added the run would be about 1,720 feet, roughly $40 per foot.

Council moved, seconded and approved the expenditure on a unanimous vote. Council members said they had seen video of the problem and agreed that completing a temporary line while work continues would prevent further interruptions for affected residents.

Staff will direct the contractor to install the temporary line and will coordinate restoration when permanent water-line work is complete.