NextLink says Lampasas fiber project 76% complete, outlines phases to finish build

City of Lampasas Mayor and Council · April 22, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

NextLink told Lampasas council it has built roughly 60 miles of network and passed about 76% of households inside the city, has completed a second independent fiber route for redundancy, and expects to restart work on remaining phases in the second half of the year with an aim to finish next year.

NextLink representative Chris Hoffman told the Lampasas mayor and council on April 16 that the company's fiber-to-the-home project in the city has reached roughly 76% completion and about 60 miles of network.

Hoffman said NextLink has prioritized redundancy after single-line fiber outages caused broad service interruptions: “Whenever a fiber line gets cut, it kinda takes down all of the surface,” he said, adding the company finished an independent second fiber route into Lampasas in October 2023 so one circuit can keep traffic flowing if the other is damaged. "Since we got that completed in…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans