Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction Projects topic

No spam. Unsubscribe anytime.

Commission accepts $25,000 credit and approves final change order for indoor pavilion

Curry County Board of Commissioners · September 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facing an 80-day delay on the Indoor Pavilion project and accumulated change orders, Curry County commissioners accepted a $25,000 contractor credit and approved a final change order that includes electrical and accessibility corrections.

The Curry County Commission approved a negotiated $25,000 credit from contractor WWRC for the Indoor Pavilion project and also approved Change Order No. 4, which county staff described as the last additive change order for the project.

Project manager Ben Roberts summarized the components covered by change order No. 4: additional electrical work to provide a second 250-amp circuit required for a commercial kitchen stove, installation of concrete bases for exterior light poles, and widening an opening in the restroom walls to meet accessibility clearance where a water fountain was to be installed. Roberts reported the assembled items on this change order total approximately $9,648.73.

Roberts said the project missed its June 30 completion deadline by roughly 80 days; liquidated damages at the contract rate could have been greater than the negotiated credit (a staff estimate placed potential liquidated damages near $40,000). County legal counsel and staff recommended accepting the contractor's $25,000 credit as a reasonable compromise, noting some delays were tied to weather and equipment delivery, and that pursuing full damages could be more costly than the settlement.

Commissioner Martin raised concerns about weekends when work might have been possible; county staff acknowledged both weather and scheduling choices by the contractor had contributed to the delay. The commission approved both the change order and acceptance of the $25,000 credit by voice/roll-call vote.

The commission asked staff to continue pursuing completion and to return with final close-out documents and the credit application for the project record.