Commission approves caliche‑spreading agreement for three county roads at $10, citing large county cost savings
Summary
The commission approved a construction services agreement with TIC to spread caliche on three county roads for a stated contract price of $10, which staff said represents an estimated approximate county savings of about $286,390 versus doing the work and buying materials in-house.
Get email alerts on the Roads Projects topic
No spam. Unsubscribe anytime.
The commission approved a construction services agreement between TIC (industrial company) and Curry County to spread caliche on three roads: County Road 23 (one mile between L and K), Curry Road A (south of NM‑77 for roughly a half mile), and County Road I (about a half mile between CR 23 and 22). Gordon (Ford) Beavers presented the agreement and said the contract price presented for acceptance was $10 total.
Beavers compared that $10 agreement to a county-performed cost estimate for the same work of approximately $286,400.96, and characterized the agreement as a county savings of roughly $286,390. He said the work provides an all-weather approach for local traffic and access to methane digester sites and will help a resident on CR‑23 who experiences mud when it rains.
A motion to approve the agreement at the stated cost was moved, seconded and approved by the commission with voice/roll-call affirmation.
Commissioners asked for funding-source details and the county manager said the manager’s office would identify where funds (if any) would be pulled from and that the county must concur on any interim or interim-management proposals related to third-party agreements.
The commission did not identify additional contract amendments at the meeting. Staff said a more detailed per-road cost breakdown could be provided on request.