Weston committee advances $2.4 million North House HVAC plan, aims for June start
Summary
District staff said a revised $2.4 million HVAC upgrade for North House is moving through design and procurement, with an RFP expected in early February and targeted installation beginning in June; the system’s phased design could allow partial occupancy while work continues.
The Weston School District’s Facilities Finance Operations Committee heard an update Jan. 16 on the North House HVAC project, where staff said design and procurement work is underway and the district hopes to start construction this June. Phil said the revised project cost is about $2,400,000 and that the board of finance unanimously approved initial funding; the board of selectmen also approved the project but procedural order may require the board of finance to revote in February.
Staff described an expedited timeline for issuing a design RFP, with drafts expected by Jan. 28–30 and a goal of posting the RFP in early February so engineering and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat