Select Board approves 61‑ft fixed pier for Edgewater Drive East property
Summary
Select Board closed a wetlands public hearing and approved a fixed, pile‑supported 61‑ft pier into Eel Pond at 202 Edgewater Drive East after the applicant said the harbor master raised no navigation concerns and a shellfish survey found acceptable density levels.
Get email alerts on the Wetlands topic
No spam. Unsubscribe anytime.
The Select Board closed the public hearing and approved an application to construct a fixed, pile‑supported pier extending roughly 61 feet seaward from a seawall at 202 Edgewater Drive East in East Falmouth.
Mike Corselli of Falmouth Engineering, representing Michael and Marnie Farrell, described the 4‑foot‑wide pier design with timber piles, profiles to accommodate tidal variation and a 3‑foot minimum water depth at mean low water. He said a shellfish survey found density thresholds were not exceeded and that the harbor master raised no navigation concerns. Corselli also noted the proposed crossing is about 18% of the pond width (≈350 feet), under the Army Corps' informal 25% crossing guideline.
No public commenters spoke in opposition at the hearing. After the Select Board closed the hearing, a motion to approve the application passed on a voice vote of members present.