Bath Central board green-lights playground bid, hears chiller and construction schedule
Summary
The board approved recommended bids for playground equipment and resurfacing as part of Phase 3 of the district capital project and received a construction update on chiller delivery, night work, demo and bus-garage site work.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Bath Central School District Board of Education on Tuesday approved recommended bids for playground equipment and resurfacing tied to Phase 3 of the district’s capital project and heard a facilities update that outlined a tentative installation timeline for a new chiller and other construction work.
A facilities speaker told the board the chiller’s three pieces of electrical gear are onsite and staged in the basement and that the chiller unit itself has arrived. The contractor completed a first crane lift for the chiller components; staff said they are planning a potential roof hoist during the Thanksgiving break, with Christmas break as a contingency. Work on interior finishes continues, crews have completed the gym floor, and demo for the middle-school main entrance and bus garage site work will begin soon. Playground equipment and resurfacing bids related to Phase 3 were reviewed by the district’s review team and recommended for award; the board approved those awards by a 5–0 vote.
Board members and operations staff emphasized night and break scheduling to minimize student disruption and said some installations will be timed around school breaks. The board took the action as part of its regular consent/business agenda.
What’s next: Staff will proceed with the procurement steps for awarded playground contracts and continue coordinating installation windows, and will report construction milestones back to the board in future administrative updates.